Arbitrations worth over EUR 50 million successfully finalized by NNDKP
11 Iulie 2023 BizLawyer
The two arbitration cases addressed the issue of ensuring compliance with the contractual procedure set out in Sub-Clause 20.1 (specific to the Contractor's claims under FIDIC contracts), as well as the issue of the Contractor's entitlement to fully recover the losses sustained both in the scenario of additional works and in the scenario of an extension of the time for completion for reasons involving risks for which the Employer is responsible.
| |
NNDKP has successfully finalized the two successive arbitration cases related to the design and execution of one of the four sections of the Sebes-Turda motorway.
These arbitrations, which started in 2017 and 2019, respectively, and spanned more than 3 years each, were related to the claims raised by the Contractor – extension of time, additional costs, loss of profit and interest having an aggregate value of over EUR 50 million, arising in connection with the performance of the same administrative contract drafted based on the FIDIC Yellow Book (1999) rules (design and build).
The two arbitration cases addressed the issue of ensuring compliance with the contractual procedure set out in Sub-Clause 20.1 (specific to the Contractor's claims under FIDIC contracts), as well as the issue of the Contractor's entitlement to fully recover the losses sustained both in the scenario of additional works and in the scenario of an extension of the time for completion for reasons involving risks for which the Employer is responsible.
These arbitrations, which started in 2017 and 2019, respectively, and spanned more than 3 years each, were related to the claims raised by the Contractor – extension of time, additional costs, loss of profit and interest having an aggregate value of over EUR 50 million, arising in connection with the performance of the same administrative contract drafted based on the FIDIC Yellow Book (1999) rules (design and build).
The two arbitration cases addressed the issue of ensuring compliance with the contractual procedure set out in Sub-Clause 20.1 (specific to the Contractor's claims under FIDIC contracts), as well as the issue of the Contractor's entitlement to fully recover the losses sustained both in the scenario of additional works and in the scenario of an extension of the time for completion for reasons involving risks for which the Employer is responsible.
Also, the cases involved submitting complex evidence aimed at clarifying the technical and financial aspects of the risk events that occurred during the performance of the contract, determining delays, and establishing the categories of costs owed to the Contractor.
The NNDKP team representing the Contractor in these disputes included Partner Valeriu Mina and Managing Associate Alexandra Măruțoiu, members of the arbitration team part of NNDKP’s Dispute Resolution practice, who have successfully handled in recent years a highly diverse range of litigation and arbitration matters related to large and medium size infrastructure projects.
The dedicated project team also included Răzvan Vlad, Partner in NNDKP’s Public Procurement and PPP practice, who provided assistance in the implementation of the contract, in filing the Contractor's claims and during their settlement using the DAB procedure.
“This decision confirms the sustained effort of the NNDKP arbitration lawyers to identify the best arguments supporting the Contractor’s entitlement to various categories of additional costs due to the occurrence of risk events qualified in the contract as being the responsibility of the Employer. Our continued involvement over the past 12 years in administrative contract enforcement litigation and in large infrastructure projects enabled us to acquire first-rate knowledge and a thorough understanding of technical issues and of how to calculate various categories of costs. We have thus consolidated a consistent judicial and arbitral practice, which is indeed a solid premise for future successes/mandates”, declared Valeriu Mina.
NNDKP’s Dispute Resolution practice led by Ana Diculescu-Șova is independently acknowledged as a market leader in litigation, arbitration, and other dispute resolution procedures. As a confirmation of its leading market status, the firm has always achieved high rankings in reputable international legal directories such as Chambers & Partners (since 2007) and The Legal 500 (since 2002). With 7 Partners coordinating a team of over 40 litigators based in Bucharest and in the firm's regional offices, NNDKP has the resources to manage complex, multi-party or multi-year cases and propose practical strategies to mitigate potential future risks.
| Publicitate pe BizLawyer? |
![]() ![]() |
| Articol 558 / 4594 | Următorul articol |
| Publicitate pe BizLawyer? |
![]() |
BREAKING NEWS
ESENTIAL
Schoenherr a asistat fondatorii Calla Oradea în vânzarea unei participații majoritare către Integral Capital Group I Echipa, coordonată de Mădălina Neagu (partner)
Mușat & Asociații anunță cooptarea fostei președinte a Curții Supreme, Corina Corbu, în poziția de Partener Coordonator al Departamentului de Litigii | Gheorghe Mușat, Senior Partner: ”Este un mare câștig pentru firmă, pentru avocații firmei, pentru clienții firmei”
Wolf Theiss a asistat Rheinmetall în legătură cu semnarea unui acord de înființare a unui joint venture cu Pirochim Victoria
Într-un an cu investigații mai tehnice și presiune pe termene, DLA Piper România așază practica de Concurență pe trei piloni - oameni, metodă, ritm, astfel încât proiectarea strategiilor, controlul probelor și continuitatea între faze să producă cele mai bune rezultate | De vorbă cu membrii unei echipe sudate, condusă de lideri cu experiență și antrenată pe industrii sensibile, despre prudență juridică și curaj tactic, cooperare internă și rigoare probatorie, bazate pe înțelegerea fină a mediului de business și utilizarea tehnologiei ca multiplicator de acuratețe
Filip & Company a oferit asistență juridică în legătură cu o nouă emisiune de obligațiuni corporative garantate de către Agroserv Măriuța, în valoare de 3 mil. €
Kinstellar asistă Integral Capital Group în achiziția unei participații majoritare la clinica de fertilizare in vitro Calla, prin subsidiara sa Embryos
Filip & Company a asistat consorțiul de bănci care a intermediat a doua emisiune de obligațiuni prin care Romgaz a atras 500 de mil. € de pe piețele internaționale| Alexandru Bîrsan (managing partner) și Olga Niță (partener) au coordonat echipa
Filip & Company a asistat BCR și BRD în legătură cu oferta publică inițială a Cris Tim Family Holding | Olga Niță (partener) și Alexandru Bîrsan (managing partner) au coordonat echipa
Clifford Chance Badea a asistat Cris-Tim Family Holding în legătură cu IPO-ul istoric în valoare de 454,35 milioane RON | Daniel Badea (Managing Partner): ”Sperăm ca succesul Cris-Tim să încurajeze și alte branduri românești să vină pe bursă”
Filip & Company a asistat DIGI Romania S.A. în legătură cu emisiunea de obligațiuni de 600 mil. €. Alexandru Bîrsan (managing partener) a coordonat echipa
LegiTeam: Zamfirescu Racoţi Vasile & Partners recrutează avocat definitiv Dreptul muncii | Consultanță
LegiTeam: Zamfirescu Racoţi Vasile & Partners recrutează avocat definitiv Real Estate | Consultanță
Citeste pe SeeNews Digital Network
-
BizBanker
-
BizLeader
- in curand...
-
SeeNews
in curand...









RSS





