CMS | Romania passes amendments to grid connection rules
26 Iunie 2025 CMS Romania
For more information on Romania’s new grid connection rules, contact your CMS client partner or the local experts Varinia Radu, Ramona Dulamea or Raluca Diaconeasa.
| |
On 1 June 2025, Order 20/2025 for amending and supplementing orders by the Romanian Regulatory Authority (ANRE) regarding grid connection regulations went into force after being approved on 27 May.
The following article outlines the main updates to the grid connection regime, highlighting both the provisions and structural clarifications introduced by Order 20.
1. Operational limitation works
The works for automation equipment required for operational limitation have been moved from the category of reinforcement works to the category of connection installation works.
2. New case for amending the grid connection permit
The grid connection permit (ATR) can be amended to introduce the limitation operation in the N-1 regime. Even in practice this was already performed. It was introduced now among other cases where ATRs may be amended.
The following article outlines the main updates to the grid connection regime, highlighting both the provisions and structural clarifications introduced by Order 20.
1. Operational limitation works
The works for automation equipment required for operational limitation have been moved from the category of reinforcement works to the category of connection installation works.
2. New case for amending the grid connection permit
The grid connection permit (ATR) can be amended to introduce the limitation operation in the N-1 regime. Even in practice this was already performed. It was introduced now among other cases where ATRs may be amended.
3. Setting a deadline for providing the financial guarantee
Order 20 explicitly sets a deadline by which the user must submit the financial guarantee required for the issuance of the ATR. It also introduces a provision stating that failure to meet this deadline will result in the invalidation of the solution study and the rejection of the connection request. The user must provide the grid operator with proof of the lodging of the financial guarantee within a maximum period of two months from the date of communication by the grid operator of the approved solution study. This refers to the financial guarantee of 5% of the grid connection tariff, which must be put in place before obtaining a new ATR. As with the old regulation, there is no deadline stipulated but only the obligation to submit such financial guarantee before obtaining the ATR.
4. New extension rules of the grid connection agreements
The most important change brought by Order 20 is the user’s right to request the extension of the grid connection agreement for successive periods of 12 months, due to the need to extend the deadline for the final energisation of the user's installation, subject to the user's provision of a financial guarantee in favour of the grid operator, valid for the entire duration of the contract extension.
The amount of the financial guarantee will be 5% of the grid connection tariff provided for in the grid connection agreement and increase by 5% of the amount of the grid connection tariff for each successive 12-month period added to the duration of the contract. The request for extension of the duration of the grid connection agreement must be registered by the user with the grid operator at least 30 calendar days before the date specified in the grid connection agreement for its termination.
The request must be accompanied by proof that the user has submitted a financial guarantee of 5%. Within a maximum of 15 days from the registration of the request, the grid operator must analyse the application and the documents submitted by the user and, if the documentation is complete, transmit the signed draft additional act to the user. Before the date of termination of the connection contract, the user must send the signed additional act to the grid operator. In the case of grid connection agreements whose term expires within 30 days of the date of entry into force of this order, the deadlines provided above (meaning the deadline of 30 days before the expiration date of agreement to submit the request for extension and 15 days term of the grid operator to send the signed addendum) must be reduced accordingly so that the term of the contract may be extended provided that the financial guarantee of 5% has been submitted to the grid operator. Also, the extension rules will be applicable for extension requests of grid connection agreements that were registered with the grid operator prior to the enforcement date of Order 20.
Within 180 days from the date of entry into force of this Order 20, grid operators and users must conclude addenda to the ongoing grid connection agreements in order to include amendments brought to the framework connection contracts (i.e. the right of the extension of the duration, etc.).
5. Deadlines for conclusion of the grid connection agreements
The Order amends the deadline for the user to send the grid operator the application for the conclusion of the grid connection agreement, from 30 to 45 calendar days before the date of expiry of the validity period of the ATR. At the same time, stages and deadlines have been included within the 45-calendar day period, during which the grid operator may request, if necessary, to complete the documentation attached to the application for the conclusion of the contract. In this case, the user is obliged to complete the documentation at least 15 calendar days before the expiry of the validity of the ATR. If the user fails to submit the application for conclusion of the contract or to complete the documentation to the operator within the specified time limits, the validity of the ATR will cease, and the grid operator will enforce the financial guarantee provided by the user.
Also, the deadline for the grid operator to send the signed draft connection contract to the user was amended from five working days to ten calendar days from the date of registration of the complete documentation for the conclusion of the contract. Where the proposed contract contains additional clauses to the framework contract, the deadline for the grid operator to send the signed draft contract is set at five calendar days. The obligation of the parties to agree on the contract’s terms sign by the expiry date of the validity of the ATR (i.e. 12 months from the date of issue) has been introduced.
6. Data to be considered by the grid operators when carrying out the calculations in the solution studies
In the preparation of a solution study, connection requests must be considered in the chronological order of submission of complete documentation.
When establishing the input data for the solution study, consumption or production sites located in the same network area are considered, which have the following:
concluded contracts for the preparation of the solution study;
solution studies drafted and endorsed by the grid operators;
issued valid ATRs;
connection certificates issued.
7. Connection to the electricity grid of 110 kV or higher
Annex 5 of the Connection Regulation, which outlines specific requirements for connections to grids operating at 110kV or above, has been revised to include several key clarifications:
It now explicitly states that the provisions of Annex 5 apply not only to shared connection solutions involving multiple users, but also to individual projects;
New connection or transformer substations must be spaced at least ten kilometres apart;
Developers who have financed new connection substations are obliged to grant access to future developers, provided they receive appropriate financial compensation from those benefiting from the shared infrastructure.
8. Extension of Temporary Conformity Certificate duration
The Temporary Conformity Certificate, which was previously limited to a single extension of up to three months, may now be extended in successive three-month periods, as long as significant progress can be demonstrated. The total duration of these extensions, however, must remain within the maximum permitted testing periods: 24 months for Category D projects and 12 months for Category C projects.
For more information on Romania’s new grid connection rules, contact your CMS client partner or the local experts Varinia Radu, Ramona Dulamea or Raluca Diaconeasa.
| Publicitate pe BizLawyer? |
![]() ![]() |
| Articol 161 / 4681 | Următorul articol |
| Publicitate pe BizLawyer? |
![]() |
BREAKING NEWS
ESENTIAL
Ritm alert, tranzacții de referință și expertiză recunoscută | Practica de Energie & Resurse Naturale a RTPR, Tier 1 în Legal 500, gestionează integrat mandate care combină M&A, finanțări verzi, autorizare și reglementare, oferind clienților internaționali și locali suport în proiecte cu miză ridicată. De vorbă cu partenerul Bogdan Cordoș despre tendințele anului 2026, interesul investitorilor și mandatele relevante
Avocații KPMG Legal – Toncescu și Asociații, implicați într-un proiect de autorizare complexă pe piața serviciilor de plată, prin care Mobile Distribution devine instituție de plată
ZRVP organizează în data de 11 iunie 2026 dezbaterea „Contractul de antrepriză: de la FIDIC la HG 1 ̸ 2018 – evoluție, adaptare sau compromis?”
KPMG integrează Claude în activitatea globală și deschide accesul la AI pentru peste 276.000 de angajați | AI-ul generativ intră în zona operațională a serviciilor profesionale, începând cu tax, legal, private equity și cybersecurity
League Tables of Legal Advisors → Cum au văzut analiștii Mergermarket piața de M&A și activitatea firmelor de avocați în primul trimestru din 2026 | Numărul tranzacțiilor a scăzut, dar valoarea cumulată are un avans de 20%. Clifford Chance, DLA Piper și CMS se remarcă la nivel global și în Europa. O activitate mai puțin intensă în CEE, cu România printre cele mai active piețe din regiune
Meet the Professionals | Cum se construiește drumul spre parteneriat într-o firmă de top și ce presupune noul statut → De vorbă cu Rebecca Marina, Filip & Company, despre ”rolul cameleonic” al unui partener și responsabilitatea discretă din spatele fiecărui mandat complex: ”Succesul nu este definit doar de finalizarea formală a tranzacției, ci de calitatea relațiilor pe care le lași în urma ta”
LegiTeam: Reff & Associates is looking for a Junior Associate | Dispute Resolution
Țuca Zbârcea & Asociații, desemnată ”Firma anului în România” la Chambers Europe Awards 2026 | Schoenherr câștigă în Europa de Sud-Est, Kinstellar în CEE, iar Mannheimer Swartling primește distincția la nivel european. Deloitte Legal, premiată ca ”Outstanding Law Firm”
Practica de Energie a firmei Bohâlțeanu și Asociații marchează unul dintre cei mai intenși ani din evoluția sa, cu mandate complexe în proiecte solare, finanțări transfrontaliere, tranzacții M&A multijurisdicționale și proiecte inovative care pot influența dezvoltarea energiei verzi în România | Ionuț Bohâlțeanu (Managing Partner): ”Planurile pentru următorul an sunt de extindere și diversificare a mandatelor în acest domeniu, urmărind implicarea în proiecte care să scoată în evidență potențialul firmei noastre”
Bucharest Arbitration Days 2026: Probele în arbitrajul internațional: principii și practici în evoluție
Meet the Professionals | Din vorbă în vorbă cu Lidia Zărnescu, recent promovată Counsel la Kinstellar despre un parcurs în Dreptul muncii construit cu răbdare și cu oameni valoroși, întâlniți la momentele potrivite: ”Văd cariera ca pe un maraton, nu ca pe un sprint; dacă se „ard” etape, se pierd lecții și valori esențiale. Cred că adevărata valoare a unui avocat stă în modul în care își folosește expertiza pentru a crea valoare pentru cei din jur”
ZRVP, distinsă cu titlul de “Romania Patent Firm of the Year” la gala Managing IP Awards 2026 | De vorbă cu Alina Tugearu (Partener) despre proprietatea intelectuală ca teren de strategie, prevenție și confruntare juridică în dosare cu miză ridicată: ”Am convingerea că implicarea în unele dintre cele mai sofisticate și relevante dosare din piață a contribuit la recunoașterea de care ne bucurăm azi”
Citeste pe SeeNews Digital Network
-
BizBanker
-
BizLeader
- in curand...
-
SeeNews
in curand...









RSS