New MADR Norms – the Good, the Bad and the Ugly for renewables

25 Octombrie 2022   |   Mihaela Nyerges, Partner - Vlăsceanu, Nyerges & Partners

The Norms have been finally adopted earlier this month. Now that they are here, what do they mean for development of renewables?

 
 
Ever since the Land Fund Law was amended to allow the development of renewables on extra murros land, the entire industry has been waiting for the Ministry of Agriculture and Rural Development (“MADR”) to issue the application norms thereof (the “Norms”).

The Norms have been finally adopted earlier this month. Now that they are here, what do they mean for development of renewables?

As a preliminary note, although the Norms were expected to clarify aspects related to projects exceeding 50 hectares, the Norms are limited to amending the procedure for removing the land from the agricultural circuit, in order to align it with the new provisions of the Land Fund Law.

1.         Surface to be removed from agricultural circuit in case of dual use of the land

The biggest gain bought by the Norms is that they clarified which sections of the land should be removed from agricultural circuit in case of dual use of the land (power generation and agricultural activities). These are the sections on which ground level constructions are being erected: such as the pillars of the mounting structure, invertors, transformers substations, storage facilities, access roads.

Therefore, in case of PV projects, it is clarified that only the land affected by the pillars should be removed from agricultural circuit, not also the land corresponding to panels projection. Such could contribute substantially to the decrease of the land removal tax, which is one of the main costs in the development process. However, the practical impact is not that high, since (i) the dual use of the land is not allowed for arable land (which is frequently the land suitable for power generation projects) and (ii) the above principles do not apply to pastures (as we will explain below).

In view of the above, the applicant should submit, among other, the technical project outlining the type of project, the placement of the project components, occupation degree, the agricultural activities to be conducted, surfaces to be used for dual purpose.

2.         Indirect limitation to developing power generation capacities inside farms only

One of the mandatory documents for removing the land from agricultural circuit in case of renewable generation capacities is the “technical project regarding the placement within the farms of the renewable power generation facilities used exclusively for the own consumption of the farms.”

This document implies that the power generation capacities may be erected only within farms and only for ensuring the power consumption of the farms. This is obviously a limitation which is no longer existing in the Land Fund Law (following the recent changes), and which may not be enacted through a legal enactment inferior to the Land Fund Law (such as the Norms).

In our view, this provision is the result of a clerical error, and we can only hope that it will be corrected shortly before causing (another) blockage in the development process.  

 

3.         Unclear land regime between land removal decision and building permit

The land is removed from the agricultural circuit through the decision adopted by the relevant county agricultural department. However, according to the Norms, the land can be registered with the Land Book as buildable land only later on in the development process, after obtaining the building permit.

It is therefore unclear the legal and tax regime of the land during the period between the land removal decision and the building permit. 

4.         Unclear rules for requalification of the land as agricultural in case of failed projects

The Norms provide that, if the investment works are not initiated within 5 years from the land removal decision, the land is requalified back as agricultural land “by virtue of law”, based on a notification sent to the relevant county agriculture department by the land removal beneficiary. 

The requalification of the land as agricultural land “by virtue of law” seems to imply that this requalification occurs automatically upon the expiry of the 5 years period, without another administrative act being needed from the authorities. However, such principle seems to be contradicted by the fact that a notification should be sent by the beneficiary. Also, if the notification is sent long time after the 5-year term, it is not clear what will be the legal and tax regime of the land in the period between the expiry of the 5-year term and the notification.

Also, judging from the experience of the first wave of renewables (after which many landowners were stuck with intra muros lands and had to face lengthy court/administrative proceedings to change back the land destination), the beneficiary may no longer have any motivation to file such request. From this perspective, it seems more appropriate that the landowner should be also allowed to file such notification in case the superficies agreements are terminated due to failed projects. 

5.         No rules for pastures

The Norms do not set out the rules applicable to pastures. The reason for this is that the Norms are amending only the general regulation applicable to agricultural removal of all types of lands (pastures excluded), without touching the regulation dedicated to pastures removal from agricultural circuit.  

It, therefore, remains to be seen whether the rules referred above regarding the dual use of the land will be replicated for pastures. Such rules will decisively influence the feasibility of developing renewables on pastures.

 
 

PNSA

 
 

ARTICOLE PE ACEEASI TEMA

ARTICOLE DE ACELASI AUTOR


 

Ascunde Reclama
 
 

POSTEAZA UN COMENTARIU


Nume *
Email (nu va fi publicat) *
Comentariu *
Cod de securitate*







* campuri obligatorii


Articol 935 / 4593
 

Ascunde Reclama
 
BREAKING NEWS
ESENTIAL
Wolf Theiss a asistat Rheinmetall în legătură cu semnarea unui acord de înființare a unui joint venture cu Pirochim Victoria
Într-un an cu investigații mai tehnice și presiune pe termene, DLA Piper România așază practica de Concurență pe trei piloni - oameni, metodă, ritm, astfel încât proiectarea strategiilor, controlul probelor și continuitatea între faze să producă cele mai bune rezultate | De vorbă cu membrii unei echipe sudate, condusă de lideri cu experiență și antrenată pe industrii sensibile, despre prudență juridică și curaj tactic, cooperare internă și rigoare probatorie, bazate pe înțelegerea fină a mediului de business și utilizarea tehnologiei ca multiplicator de acuratețe
Filip & Company a oferit asistență juridică în legătură cu o nouă emisiune de obligațiuni corporative garantate de către Agroserv Măriuța, în valoare de 3 mil. €
Kinstellar asistă Integral Capital Group în achiziția unei participații majoritare la clinica de fertilizare in vitro Calla, prin subsidiara sa Embryos
Filip & Company a asistat consorțiul de bănci care a intermediat a doua emisiune de obligațiuni prin care Romgaz a atras 500 de mil. € de pe piețele internaționale| Alexandru Bîrsan (managing partner) și Olga Niță (partener) au coordonat echipa
Filip & Company a asistat BCR și BRD în legătură cu oferta publică inițială a Cris Tim Family Holding | Olga Niță (partener) și Alexandru Bîrsan (managing partner) au coordonat echipa
Clifford Chance Badea a asistat Cris-Tim Family Holding în legătură cu IPO-ul istoric în valoare de 454,35 milioane RON | Daniel Badea (Managing Partner): ”Sperăm ca succesul Cris-Tim să încurajeze și alte branduri românești să vină pe bursă”
Filip & Company a asistat DIGI Romania S.A. în legătură cu emisiunea de obligațiuni de 600 mil. €. Alexandru Bîrsan (managing partener) a coordonat echipa
LegiTeam: Zamfirescu Racoţi Vasile & Partners recrutează avocat definitiv Dreptul muncii | Consultanță
LegiTeam: Zamfirescu Racoţi Vasile & Partners recrutează avocat definitiv Real Estate | Consultanță
Țuca Zbârcea & Asociații obține o soluție favorabilă într-un important litigiu de drept fiscal și vamal | Ionuț Șerban (Partener): „Este o victorie importantă pentru clientul nostru și un precedent valoros în disputele de drept vamal”
Avocații PNSA au stat alături de M Plus Croatia d.o.o, lider european în outsourcing-ul proceselor de afaceri și tehnologie, în tranzacția prin care a achiziționat Valoris Group - jucător local care deservește proiecte multilingve pentru clienți internaționali | Echipa pluridisciplinară a fost coordonată de partenerul Bogdan C. Stoica
 
Citeste pe SeeNews Digital Network
  • BizBanker

  • BizLeader

      in curand...
  • SeeNews

    in curand...