ZRP
Tuca Zbarcea & Asociatii

Happy start of the year for the Romanian electricity market

10 Ianuarie 2022   |   Mihaela Nyerges, Partner - Vlăsceanu, Nyerges & Partners

Adopting GEO 143/2021 was a must for Romanian authorities as Romanian was much behind the European deadlines as regard the implementation of the European legislation part of the Clean Energy for all Europeans package.

Mihaela Nyerges, Partner - Vlăsceanu, Nyerges & Partners

 
 
The very last days of 2021 kept Government busy amending the Electricity and gas law no. 123/2012 (the “Energy Law”) by adopting Emergency Ordinance no. 143/2021 amending and supplementing the Energy Law, as well as amending other legal enactments (“GEO 143/2021”). GEO 143/2021 gives a pretty good start to 2022 for the Romanian electricity market.

Adopting GEO 143/2021 was a must for Romanian authorities as Romanian was much behind the European deadlines as regard the implementation of the European legislation part of the Clean Energy for all Europeans package. Although some of the new provisions are merely taking over existing principles from other Romanian legal enactments, some of the changes are highly important for all stakeholders of the electricity market. Below you may find few highlights of such changes.

1.            PPA ban was removed

After a ban which lasted almost a decade, participants on the wholesale electricity market are again allowed to enter into directly negotiated power purchase agreements, irrespective the installed capacity or commissioning date of the power plants.

The PPA ban was one of the most controversial and disputed interventions of the Romanian legislator which significantly influenced the faith of the Romanian energy sector during the past decade. It contributed substantially to the failure of several important power generation projects for which the Romanian state was under advanced negotiations with foreign investors. It also caused lack of new investments in the sector.

The reason behind such strong impact was that securing financing for the development of new power plants depends on the execution of long term PPAs, as a guarantee for a stable cash flow. However, since PPAs could not be concluded outside OPCOM markets (on which only operational producers had access), developers had no possibility to enter conclude PPAs. Although, more than a year ago, OPCOM created a special platform dedicated to the execution of long term PPAs by developers of new power plants, such platform was a complete failure as no participants have been ever registered on such platform. Such made it even more clear that the direct negotiation of the PPA terms between the parties and the financing banks is essential for the successful execution thereof.

The pressure to eliminate the ban came from multiple sides. The need to replace old coal-based power plants combined with new ambitious mandatory E-RES targets imposed from EU level, made investments in Romanian power generation capacities a high priority. In addition, Regulation 2019/943 of the European Parliament and of the Council on the internal market for electricity, which became directly applicable in Romania starting from January 2020 imposed Member States the obligation to eliminate barriers to the execution of directly negotiated PPAs.

GEO 143/2021 requires, however, state owned/controlled producers to trade at least 40% of the annual electricity generated through contracts concluded on power exchanges, so as to increase the liquidity of the market.

2.            ANRE remains competent to issue setting-up authorizations for building new power plants

According to the draft GEO 143/2021 submitted by the Ministry of Energy for public consultations, the issuance of the setting-up authorizations (which are necessary for building new power plants) was to be transferred from the competence of the Romanian Energy Regulatory Authority (“ANRE”) to that of the Ministry of Energy. In addition, such was to be issued before securing the right to connect the power plant to the power grid (through the issuance of the grid connection permit - ATR).

This proposed change showed a lack of understanding of the fundamentals of the permitting process of power generation capacities on the following main grounds:

·               considering the limited capacity of the grid, a key milestone in determining a project’s feasibility is securing the right to connect to the grid. This is the reason why investments in such projects are kept to a minimum until the ATR is obtained;

·               the issuance of the setting-up authorization is subject to a tariff of (i) 0.1% of the value of the project (for projects having a capacity below 100 MW) and of (ii) 0.05% of the value of the projects (for projects having a capacity above 100 MW); hence, the payment of such tariff should occur at a point where the feasibility of the project is a certainty; and

·               the issuance of the setting-up authorization is conditional upon showing the availability of the funds; in the cases where external financing is sought, no financial institution would provide such financing before the ATR is secured.  

Considering the above, the main industry associations in Romania sent an official letter to the Ministry of Energy explaining the problems that would be caused by such a change, if approved.

Fortunately, the final version of the GEO 143/2021 eliminates the above provisions, so that the issuance of the setting-up authorizations stays in the competence of the ANRE. ANRE must inform, though, the Ministry of Energy, on a weekly basis, regarding all applications received for the issuance of setting-up authorizations.

3.            Trading mechanism suitable for small producers

OPCOM must implement trading mechanisms for the Day-Ahead market and the Intra-Day to allow offers of 500kW or less.

4.            New provisions applicable to prosumers

The GEO 143/2021 introduces new principles meant to encourage investments by prosumers:

·               it is increased from 100kW to 400kW the capacity of prosumers’ installations for which prosumers are allowed to sell to their suppliers the electricity thus generated;

·               the commercial rules for such sale differ depending on the installed capacity of the prosumers’ installations:

(i)                 prosumers with installations of up to 200kW will benefit from quantitative compensation between the electricity consumed from the grid and that injected into the grid, with the electricity consumed in excess being invoiced and that injected in excess being available for consumption during the next 24 months; such rules apply only until December 31, 2030, after which the same rules set out below shall become applicable; and

(ii)              prosumers with installations between 200kW and 400kW sell the electricity at the average weighted Day-Ahead Market.

·               prosumers with installations not exceeding 400kW are exempted from balancing responsibilities, which are taken over by the suppliers.

Within 6 months from the entering into force of GEO 143/2021 (i.e. by the end of June this year), ANRE must amend the secondary legislation so as to align it to the new principles laid down by GEO 143/2021. Therefore, we should expect a very intense and interesting activity of ANRE in the next period.

We can only hope that GEO 143/2021 paves the way to a stable legal framework which is essential for the Romanian energy sector to attract the investments it desperately needs.


 
 

PNSA

 
 

ARTICOLE PE ACEEASI TEMA

ARTICOLE DE ACELASI AUTOR


 

Ascunde Reclama
 
 

POSTEAZA UN COMENTARIU


Nume *
Email (nu va fi publicat) *
Comentariu *
Cod de securitate*







* campuri obligatorii


Articol 1699 / 4653
 

Ascunde Reclama
 
BREAKING NEWS
ESENTIAL
România a pierdut arbitrajul ICSID cerut de mai mulți dezvoltatori de parcuri fotovoltaice. Comitetul ad-hoc format din trei arbitri a respins cererea de anulare a hotărârii Tribunalului prin care statul român a fost obligat să plătească peste 40 mil. € | Reclamanții au mers cu King & Spalding (Houston și Paris), apărarea a fost asigurată de o firmă americană și una locală
Exim Banca Românească, parte a consorțiului internațional de bănci care finanțează Ogrezeni, unul dintre cele mai mari proiecte hibride din Europa, cu 460 mil. € | Schoenherr și Clifford Chance Badea, în tranzacție
BERD, CEECAT Capital și Morphosis Capital își marchează exitul din investiția în La Cocoș. Osborne Clarke, Van Campen Liem și Noerr, în tranzacție, alături de trei firme locale de avocați
LegiTeam: CMS CAMERON MCKENNA NABARRO OLSWANG LLP SCP is looking for: Associate | Commercial group (3-4 years definitive ̸ qualified lawyer)
Popescu & Asociații rămâne un reper de seriozitate și profunzime, cu o cultură care privilegiază calitatea, consecvența și responsabilitatea | De vorbă cu Adrian Chirvase (Partener) despre 2025 ca an de consolidare: portofoliu diversificat, retenție ridicată, tehnologie folosită pragmatic și o echipă unită, pregătită pentru mandate transfrontaliere
Filip & Company a asistat Veranda Obor S.A. în obținerea unei finanțări de 36 milioane euro de la CEC Bank. Echipa, coordonată de Alexandra Manciulea (partner) și Rebecca Marina (counsel)
O promovare din interior care confirmă meritocrația și creșterea organică într-una dintre cele mai puternice firme de avocatură din România | De vorbă cu Ramona Pentilescu, avocatul care a crescut în PNSA de la primii pași în profesie până la poziția de partener, despre vocație, rigoare și reperele care i-au susținut evoluția profesională într-un cadru în care contează respectul pentru profesie și coerența valorilor
Neagu Dinu Partners, firmă înființată anul trecut, își face rapid loc în prim-planul practicii de Litigii & Arbitraj din piața locală, cu un model de lucru pragmatic, în care partenerii cooordonează dosarele și păstrează controlul calității în mandate complexe | De vorbă cu Simona Neagu (Partener fondator) despre așteptările tot mai ridicate ale clienților, colaborările internaționale și disciplina internă care susține performanța echipei
LSEG Deals Intelligence | Cum s-au împărțit fuziunile mid-market, anul trecut, pe firmele de avocatură active și la București. CMS a fost pe podium în Europa și pe primul loc în Estul continentului, unde s-au mai evidențiat Schoenherr și Clifford Chance. Tranzacții mai multe, dar de valoare mai mică în Europa Estică
Studenții la Drept sunt invitați la Turneul de dezbateri „Law and Life in Contest” organizat de Bondoc și Asociații
LegiTeam | RTPR is looking for a litigation lawyer (3-4 years of experience)
ICC Arbitration Breakfast revine în România cu cea de-a doua ediție - 18 martie, în București
 
Citeste pe SeeNews Digital Network
  • BizBanker

  • BizLeader

      in curand...
  • SeeNews

    in curand...