09 Mai 2022   |   Mihaela Nyerges, Partner Vlăsceanu, Nyerges & Partners

In the pursuit of suitable lands, pastures have entered the close attention of developers.

 
 
Romania has a high potential of renewable energy sources (RES) distributed on its entire territory. Nevertheless, when selecting the location of a E-RES generation project, multiple criteria must be used such as distance to the grid, availability of grid capacity, absence of technical or urbanism limitations.

In the pursuit of suitable lands, pastures have entered the close attention of developers.

Romania has more than 4 million pastures, many of which strategically located. However, the vast majority of Romanian pastures are extra murros land, which triggers the application of a very strict legal regime. The purpose thereof is to ensure that the total surface of pastures inventoried in July 2007 is not being diminished.

According to Government Emergency Ordinance no. 34/2013 on the organization, administration and operation of permanent pastures and for amending and supplementing the Land Law no. 18/1991 (Pastures Ordinance”), the pastures located extra murros may be used only for animal grazing and fodder production.

By exception, the extra murros pastures may be used for building specific types of constructions among which the E-RES generation capacities. Nevertheless, the development of E-RES projects on extra-murros pastures is subject to specific mandatory requirements that, in practice, prove to be deadlocks.  

According to Pastures Ordinance, such requirements are the following:

(i)              the E-RES projects must not affect the good exploitation of the pastures; and

(ii)           the developer must recover from the non-productive lands an area equal to that of the pasture which is removed from the agricultural circuit.

On one hand, the 2 conditions seem to overlap. We do not see the rationale for which the E-RES capacities should not affect the good exploitation of the pastures if a corresponding area of non-productive land is to be recovered to account for the respective pasture.

In addition, from a practical perspective, non-productive land is extremely hard to find. As result, considering the big surface of land needed for developing a solar project, the land recovering requirement ultimately makes ineffective the right to develop such projects on pastures.

A practical solution for ensuring the coexistence between solar projects and pastures is to install higher pillars that would allow animal grazing and fodder production under the panels. Under such a scenario, it should be sufficient to remove from agricultural circuit and, therefore, to recover from non-productive land only the area covered by specific segments of the photovoltaic park (such as pillars and transformer substation), as such would be the only area that becomes unexploitable as pasture.

Nevertheless, the above solution should be deemed acceptable by the Ministry of Agricultural and Rural Development, as such authority should favorably endorse the removal of the pastures from the agricultural circuit (for areas below 100 ha).

Another solution could come from a draft of law that is currently on the agenda of the Deputies Chamber. According to such draft, it is allowed to build E-RES projects on extra murros land, including pastures, to the extent not exceeding 50 ha. If such law is approved (and wording slightly clarified and corelated to existing legislation), not only that the harsh requirements imposed by Pastures Ordinance would no longer be applicable, but no PUZ would be needed for developing E-RES projects on extra murros pastures. Such would considerably speed up the development process.

While Romanian lawmaker and authorities continue to be puzzled by the “green pastures” – “green power projects” dilemma, more and more studies and countries support the development of agrivoltaic projects, and numerous such projects are being implemented worldwide. We can only hope for a favorable solution that would give a boost to E-RES development in Romania.  

 
 

PNSA

 
 

ARTICOLE PE ACEEASI TEMA

ARTICOLE DE ACELASI AUTOR


     

    Ascunde Reclama
     
     

    POSTEAZA UN COMENTARIU


    Nume *
    Email (nu va fi publicat) *
    Comentariu *
    Cod de securitate*







    * campuri obligatorii


    Articol 925 / 4263
     

    Ascunde Reclama
     
    BREAKING NEWS
    ESENTIAL
    Senior Lawyer Employment | Reff & Associates
    BACIU PARTNERS: Rafinarea serviciilor juridice oferite într-o manieră integrată pentru o realitate în continuă schimbare | Ana-Maria Baciu, Managing Partner: “Am coordonat mereu echipe de avocați atipice, și acum am decis să creștem tempo-ul: suntem pregătiți să facem modul nostru de a gândi și de a pune în practică lucrurile să se reflecte clar, fără obstacole, în toate inițiativele în care suntem implicați”
    Filip & Company a asistat grupul Digi la contractarea unui două împrumuturi în valoare peste 117 mil. € și, respectiv, de 50 mil. €
    Proiectul parcului fotovoltaic de la Ovidiu face un pas înainte. MPR|Partners a fost alături de EnPower Energy pentru coordonarea procedurii de obținere a acordului de construire, cu o echipă de avocați coordonată de Gelu Maravela (partener fondator) și Dana Rădulescu (partener)
    Finanțele au demarat procedura de selecție a firmelor de avocați pentru un proiect ce presupune asistență consistentă în baza dreptului englez. Contract pe 3 ani, tarife orare de cca. 1.900 lei
    Cine sunt și cum gândesc profesioniștii evidențiați de Legal 500 în GC Powerlist Romania | De vorbă cu Alexandru Berea, General counsel la BCR: ”Prin colaborare putem genera schimbări semnificative nu doar în interiorul profesiei noastre, ci și în societate in general. Prin natura muncii noastre, nu numai că răspundem la nevoile imediate ale societății, dar suntem și arhitecți ai viitorului acesteia, contribuind la definirea și modelarea unui cadru normativ care să orienteze comportamentul și deciziile individuale și colective pe termen lung”
    Rebecca Marina, counsel în cadrul firmei Filip & Company după ultima rundă de promovări: “Am găsit aici oameni care îmi împărtășesc principiile și valorile de viață și care mi-au devenit prieteni și mentori sau pentru care eu am devenit mentor mai târziu. Orice promovare vine cu responsabilități și noi roluri în echipă”
    Patru case locale de avocați rămân în topul global al celor mai bune 100 de firme implicate în arbitraje internaționale | Cum sunt prezentate în GAR 100 (2024), ce mandate au avut și ce spun clienții despre avocați și prestațiile acestora. TZA, ZRVP, LDDP și SP asistă clienți în arbitraje cu pretenții de 15,7 miliarde de dolari
    Kinstellar a asistat BIG Mega Renewable Energy cu privire la finanțarea de 92 mil. € cu BERD și OTP Bank pentru construcția și operarea Parcului Eolian Urleasca
    Răzvan Gheorghiu-Testa, fondator al Țuca Zbârcea & Asociații, inclus în „Top 50 Cei Mai Influenți Oameni de pe Piața Imobiliară din România”
    Wolf Theiss a asistat AIRSOL în legătură cu achiziția MedAir Oxygen Solution | Emanuele Lainati, Legal Affair Manager SOL Group: “Expertiza, dedicarea și abordarea proactivă a avocaţilor Wolf Theiss au fost esențiale pentru încheierea cu succes a tranzacției”
    Filip & Company a asistat Centrokinetic, în parteneriat cu Agista, în achiziția pachetului majoritar de părți sociale ale clinicii Socrates din Timișoara
     
    Citeste pe SeeNews Digital Network
    • BizBanker

    • BizLeader

        in curand...
    • SeeNews

      in curand...