ZRP
Tuca Zbarcea & Asociatii

Developing Renewables in Romania: PUZ or Pass?

17 Octombrie 2022   |   Mihaela Nyerges, Partener - Vlăsceanu, Nyerges & Partners

The practice of the authorities seems to differ: there are local authorities that request a PUZ for the issuance of the building permit, and authorities that no longer impose such an obligation through the urban planning certificate.

 
 

One of the most frequent questions asked there days by renewables investors and developers is whether PUZ is still required for developing small renewable power projects in Romania (below 50 ha). The relevance of this question is huge as the answer impacts on the duration of the development process with up to 9 months.

To answer, brief preliminary comments should be made regarding the general construction permitting rules, depending on the various types of lands.

1.          Types of lands

The following lands qualifications are relevant for the current topic:

(i)         from the perspective of their location, the lands can be (a) located intra-muros (within the buildable perimeter of the respective territorial administrative unit) or (b) located extra-muros (outside such perimeter);

(ii)       from the perspective of their destination, the lands can be, among others, (a) agricultural lands or (b) yards-constructions lands;

(iii)      from the perspective of their fertility class, the agricultural lands are split into 5 fertility classes, ranging from very fertile land (Class I) to very low fertile land (Class V); the fertility class is established based soil analysis made by experts within the county Office of Pedological Studies.

2.          General construction rule

As a general rule, all constructions may be erected only on lands (i) located intra-muros and (ii) qualifying as “yards-constructions”.

If the targeted land qualifies as extra-muros and agricultural land (which is typically the case with the land suitable for renewable projects),

(i)         the land should be first requalified from extra-muros into intra-muros land by means of a PUZ;

(ii)       no additional formalities should be done for converting the land from agricultural land to “yards-construction” land, as such conversion occurs automatically through the issuance of the building permit.

3.          Exception dedicated to renewable energy projects

Late July this year, an exception from the above rule was adopted, expressly allowing the construction of renewable power generation projects on extra-murros lands if the following conditions are met:

(i)         land has fertility class III, IV and V; and

(ii)       land does not exceed 50 ha.

Therefore, projects falling within the above limitations no longer need to obtain requalification of the land from extra-muros to intra-murros land through a PUZ.

4.          Need of a PUZ in case of renewable projects below 50 ha

Therefore, do we still need or not a PUZ for developing renewable on land with fertility class III, IV and V which does not exceeds 50 ha?

The practice of the authorities seems to differ: there are local authorities that request a PUZ for the issuance of the building permit, and authorities that no longer impose such an obligation through the urban planning certificate. We have also encountered a case where the authority changed its mind after having issued an urban planning certificate whereby no PUZ was requested.

Nevertheless, it should be mentioned that PUZ has multiple roles, not just the introduction of land into intra-murros area, as explained below:

(i)            according to the general construction law (with certain exceptions not applicable hereto), the building permit may be issued only if (a) there is an urban documentation approved regarding the respective land, setting out the legal, technical and economical regime of the land and (b) the envisaged construction is compatible with the rules set out by the respective urban documentation;

(ii)          all communes and towns in Romania must have an urban documentation approved – namely a general urban plan (“PUG”) adopted by the local authorities setting out (a) the function of each land (such as residential, industrial etc.) and (b) the applicable urbanism parameters and limitations (such as land occupation percentage, land occupation coefficient, height regime, etc.);

(iii)        PUG is a sufficient urbanism documentation for the issuance of a building permit if (a) it provides the legal, technical and economical regime of the targeted land and (b) the envisaged project is compatible with the regime set out thereby;

(iv)        if (a) the PUG does not provide the legal, technical and economical regime of the targeted land or (b) the envisaged construction is not compatible with the rules set out by the PUG for the targeted land or (c) there is no PUG in place (for example, it was never approved, it expired, it was cancelled in court or suspended), the developer must obtain a zonal urban plan (“PUZ”) whereby to adopt/amend the urbanism rules so that they are compatible with the project;

(v)          generally, PUGs do not regulate extra-muros land or do not establish an urbanism function/regime compatible with renewable projects;

(vi)        very recently, a new exception from the need to adopt an urbanism documentation was added in case of other specific types of constructions allowed on extra murros land.

Further to the above, PUZs are still needed for developing renewable projects on lands below 50 ha in order to establish the function and urbanism parameters of the respective land that are compatible with the envisaged project. Nevertheless, a case-by-case assessment should be made regarding the PUG rules applicable on the respective land. Such assessment should be made by the consultants of the developer, without simply relying on the assessment made by the local authorities when issuing the urbanism certificate.

 
 

PNSA

 
 

ARTICOLE PE ACEEASI TEMA

ARTICOLE DE ACELASI AUTOR


 

Ascunde Reclama
 
 

POSTEAZA UN COMENTARIU


Nume *
Email (nu va fi publicat) *
Comentariu *
Cod de securitate*







* campuri obligatorii


Articol 766 / 4405
 

Ascunde Reclama
 
BREAKING NEWS
ESENTIAL
ZRVP: 30 de ani de tradiție în avocatură, un nou look pentru viitor | Cosmin Vasile (managing partner): Noua imagine reflectă identitatea și tradiția brandului nostru, reinterpretate într-o manieră modernă și îndrăzneață
Edward Sukyas pierde arbitrajul cu statul român și trebuie să plătească peste o jumătate de milion de euro - cheltuieli arbitrale și onorarii plătite avocaților care au apărat România. Litigiul cu Jack Sukyas merge mai departe, modul de alocare a cheltuielilor de arbitraj fiind decis într-o etapă ulterioară a procedurii | Cât au însumat onorariile primite de avocații români aflați de-o parte și alta a baricadei și ce sume au încasat arbitrii
Cum a fost anul 2024 pentru Duțescu & Partners: poziționare în topul internațional al firmelor de avocați evidențiate în practica de Capital Markets, lansarea practicii de drept islamic și multe victorii obținute pentru clienți | De vorbă cu Dr. Cristian Duțescu (partener fondator) și Casiana Dușa (partener) despre parcurs, proiecte și realizări
Precedent important obținut de RTPR pentru Premier Energy Furnizare în materia teoriei impreviziunii. Despăgubiri de aproximativ 4 milioane EUR și dobânzi legale penalizatoare, ca urmare a neexecutării unui contract de furnizare de energie încheiat pe piața PCCB-BC. Alexandru Stănoiu (Counsel) și Ana Popa (Senior Associate), în echipa coordonată de Valentin Berea (Partener)
Bulboacă și Asociații facilitează atragerea de finanțare, la final de an, pentru o companie românească de succes din industria panificației
Pentru echipa de insolvență de la Țuca Zbârcea & Asociații, anul 2024 s-a caracterizat printr-o intensificare a volumului de muncă, cu mandate noi care s-au adăugat unui portofoliu existent bogat. Cele mai multe proiecte au avut complexitate și miză ridicată, necesitând extinderea echipelor implicate și un volum mai intens de activitate | De vorbă cu Cătălina Mihăilescu (Partener) despre activitatea departamentului și planurile de viitor
INTERVIURI 2+1 | Povestea lui “Timi”, numele de alint al biroului NNDKP din Nord-Vestul țării, înființat acum 20 de ani într-o perioadă fără smartphone, Google sau LinkedIn, spusă de doi avocați care au trăit intens toate etapele devenirii sale ca furnizor pentru mediul de afaceri local, standard de etică și membru al comunității academice: ”Vineri la prânz încă nu se născuse ideea; luni, la 10:15, era aprobată”. Mai apoi, ”cu profesionalism, corectitudine și smerenie” a devenit ”un organism viu și adaptabil, care se modelează după viața afacerilor din regiune în fiecare moment”
Meet the Professionals | Din vorbă în vorbă cu Cristina Roșu, proaspăt promovată Partner în cadrul firmei Toncescu și Asociații - KPMG Legal: “Angajarea mea la KPMG Legal după terminarea facultății a fost punctul de plecare al unei călătorii profesionale frumoase și pline de satisfacții, care m-a adus unde sunt astăzi. Am crescut încet, dar constant, în această firmă, dezvoltându-mă ca profesionist, dar mai ales ca om”
Echipa Wolf Theiss dedicată proiectelor din materia insolvenței este în proces de creștere și consolidare, având în vedere interesul ridicat acordat acestui domeniu și creșterea numărului și complexității proiectelor. ”În perioada recentă, ne-au fost solicitate de către clienți numeroase analize privind posibila deschidere a procedurii insolvenței, efectele și riscurile unei astfel de proceduri, dar și opțiunile reglementate pentru restructurarea afacerii, ceea ce arată interesul crescut al companiilor în utilizarea mecanismelor legale”, spun avocații
Băiculescu & Asociații continuă extinderea. Alți doi avocați se alătură firmei, întărind departamentele de Drept Penal și Litigii | Vasile Băiculescu (Managing Partner): ”Fundația unei societăți de avocatură este formată din echipe solide, orientate spre soluții și dedicare pentru client. Continuăm să creștem pentru a oferi un serviciu de calitate”
Insolvență ̸ Restructurare | În spatele scenei, alături de echipa NNDKP, într-o discuție cu trei dintre coordonatorii acestui segment de practică ce a generat venituri de cca. 11 % din total, anul trecut. Debt-recovery rămâne în continuare o parte importantă din activitatea echipei. Focusul tinde să migreze spre procedurile de pre-insolvență, iar componenta de turnaround și restructurare crește în mod constant. Numărul procedurilor de insolvență va crește cu 10-12% în următorii doi ani, estimează avocații
Bondoc și Asociații obține o clarificare importantă la ÎCCJ cu privire la stabilirea competenței pentru soluționarea litigiilor în legătură cu încheierea contractelor finanțate din fonduri alocate prin PNRR, de către beneficiari privați care nu au obligația aplicării procedurilor de achiziție publică
 
Citeste pe SeeNews Digital Network
  • BizBanker

  • BizLeader

      in curand...
  • SeeNews

    in curand...