ZRP
Tuca Zbarcea & Asociatii

Developing Renewables in Romania: PUZ or Pass?

17 Octombrie 2022   |   Mihaela Nyerges, Partener - Vlăsceanu, Nyerges & Partners

The practice of the authorities seems to differ: there are local authorities that request a PUZ for the issuance of the building permit, and authorities that no longer impose such an obligation through the urban planning certificate.

 
 

One of the most frequent questions asked there days by renewables investors and developers is whether PUZ is still required for developing small renewable power projects in Romania (below 50 ha). The relevance of this question is huge as the answer impacts on the duration of the development process with up to 9 months.

To answer, brief preliminary comments should be made regarding the general construction permitting rules, depending on the various types of lands.

1.          Types of lands

The following lands qualifications are relevant for the current topic:

(i)         from the perspective of their location, the lands can be (a) located intra-muros (within the buildable perimeter of the respective territorial administrative unit) or (b) located extra-muros (outside such perimeter);

(ii)       from the perspective of their destination, the lands can be, among others, (a) agricultural lands or (b) yards-constructions lands;

(iii)      from the perspective of their fertility class, the agricultural lands are split into 5 fertility classes, ranging from very fertile land (Class I) to very low fertile land (Class V); the fertility class is established based soil analysis made by experts within the county Office of Pedological Studies.

2.          General construction rule

As a general rule, all constructions may be erected only on lands (i) located intra-muros and (ii) qualifying as “yards-constructions”.

If the targeted land qualifies as extra-muros and agricultural land (which is typically the case with the land suitable for renewable projects),

(i)         the land should be first requalified from extra-muros into intra-muros land by means of a PUZ;

(ii)       no additional formalities should be done for converting the land from agricultural land to “yards-construction” land, as such conversion occurs automatically through the issuance of the building permit.

3.          Exception dedicated to renewable energy projects

Late July this year, an exception from the above rule was adopted, expressly allowing the construction of renewable power generation projects on extra-murros lands if the following conditions are met:

(i)         land has fertility class III, IV and V; and

(ii)       land does not exceed 50 ha.

Therefore, projects falling within the above limitations no longer need to obtain requalification of the land from extra-muros to intra-murros land through a PUZ.

4.          Need of a PUZ in case of renewable projects below 50 ha

Therefore, do we still need or not a PUZ for developing renewable on land with fertility class III, IV and V which does not exceeds 50 ha?

The practice of the authorities seems to differ: there are local authorities that request a PUZ for the issuance of the building permit, and authorities that no longer impose such an obligation through the urban planning certificate. We have also encountered a case where the authority changed its mind after having issued an urban planning certificate whereby no PUZ was requested.

Nevertheless, it should be mentioned that PUZ has multiple roles, not just the introduction of land into intra-murros area, as explained below:

(i)            according to the general construction law (with certain exceptions not applicable hereto), the building permit may be issued only if (a) there is an urban documentation approved regarding the respective land, setting out the legal, technical and economical regime of the land and (b) the envisaged construction is compatible with the rules set out by the respective urban documentation;

(ii)          all communes and towns in Romania must have an urban documentation approved – namely a general urban plan (“PUG”) adopted by the local authorities setting out (a) the function of each land (such as residential, industrial etc.) and (b) the applicable urbanism parameters and limitations (such as land occupation percentage, land occupation coefficient, height regime, etc.);

(iii)        PUG is a sufficient urbanism documentation for the issuance of a building permit if (a) it provides the legal, technical and economical regime of the targeted land and (b) the envisaged project is compatible with the regime set out thereby;

(iv)        if (a) the PUG does not provide the legal, technical and economical regime of the targeted land or (b) the envisaged construction is not compatible with the rules set out by the PUG for the targeted land or (c) there is no PUG in place (for example, it was never approved, it expired, it was cancelled in court or suspended), the developer must obtain a zonal urban plan (“PUZ”) whereby to adopt/amend the urbanism rules so that they are compatible with the project;

(v)          generally, PUGs do not regulate extra-muros land or do not establish an urbanism function/regime compatible with renewable projects;

(vi)        very recently, a new exception from the need to adopt an urbanism documentation was added in case of other specific types of constructions allowed on extra murros land.

Further to the above, PUZs are still needed for developing renewable projects on lands below 50 ha in order to establish the function and urbanism parameters of the respective land that are compatible with the envisaged project. Nevertheless, a case-by-case assessment should be made regarding the PUG rules applicable on the respective land. Such assessment should be made by the consultants of the developer, without simply relying on the assessment made by the local authorities when issuing the urbanism certificate.

 
 

PNSA

 
 

ARTICOLE PE ACEEASI TEMA

ARTICOLE DE ACELASI AUTOR


 

Ascunde Reclama
 
 

POSTEAZA UN COMENTARIU


Nume *
Email (nu va fi publicat) *
Comentariu *
Cod de securitate*







* campuri obligatorii


Articol 884 / 4522
 

Ascunde Reclama
 
BREAKING NEWS
ESENTIAL
LegiTeam | Mitel & Asociații recrutează avocat cu experiență (Litigii și Soluționare a Disputelor)
Cine sunt campionii pieței locale evidențiați în ultimul clasament IP Stars 2025 | Baciu Partners are cele mai multe recomandări în prima bandă din domeniul mărcilor. ZRVP și Dincă & Speciac sunt pe primul palier al performanței, urmate de Mușat & Asociații și NNDKP
LegiTeam: Lawyer - Corporate M&A | Reff & Associates
Kinstellar asistă Special Flanges pe toate aspectele, tranzacționale și de taxe, în achiziția producătorului industrial român Vilmar SA, cu o echipă pluridisciplinară coordonată de Zsuzsa Csiki (Partener, Co-Head of Corporate M&A) | Skadden, Simmons&Simmons și alte două firme de avocați din România au fost de o parte și de alta în această tranzacție
CMS, alături de Bitdefender la achiziția Mesh Security | Horea Popescu (Managing Partner CMS România) și Mircea Moraru (Senior Counsel), în echipa multidisciplinară coordonată de la Londra, care a oferit consultanță cumpărătorului în toate aspectele tranzacției supusă acum aprobărilor din partea autorităților de reglementare
“Schimbare” este cuvântul de ordine pe piața muncii, spun avocații de Employment de la Mușat & Asociații, fenomenul fiind potențat de avansul tehnologic rapid, evoluția așteptărilor angajaților și necesitatea adaptării la noile realități economice și sociale | Echipa gestionează un număr mare de proiecte care implică restructurări ample ale companiilor multinaționale, creşterea numărului de litigii fiind evidențiată în analiza tendințelor observate. De vorbă cu membrii echipei despre mandatele strategice încredințate de companii lideri în industrii variate și provocările anului 2025
CMS își consolidează echipa din România prin promovarea a șapte avocați | Horea Popescu, managing partner CMS România: ”Aceste promovări reflectă nu doar calitatea muncii lor, ci și energia și dedicarea cu care aduc rezultate remarcabile clienților noștri și ne poziționează perfect pentru a ne continua creșterea și dezvoltarea competențelor”
O gamă variată de mandate pentru avocații de Employment de la Mitel & Asociații | Schimbările din zona legislației muncii și noile tendințe în politica de personal, analizate de Mădălina Mitel (Partener) și Cristina Dan (Counsel)
LegiTeam | Mitel & Asociații recrutează avocat definitiv (Drept Societar și Comercial)
LegiTeam | Mitel & Asociații recrutează avocat definitiv (Real Estate)
Women in Business Law EMEA Awards 2025 | Patru case locale independente de avocați și două birouri ale unor firme internaționale, pe lista scurtă pentru titlul de “Firma anului în România”. NNDKP, CMS și Schoenherr, printre premianți, Popescu & Asociații, listată în trei categorii. Ce avocați români sunt în prim plan, anul acesta
LegiTeam | Mitel & Asociații caută avocat stagiar pentru practica de Drept Societar și Comercial
 
Citeste pe SeeNews Digital Network
  • BizBanker

  • BizLeader

      in curand...
  • SeeNews

    in curand...