ZRP
Tuca Zbarcea & Asociatii

Developing Renewables in Romania: PUZ or Pass?

17 Octombrie 2022   |   Mihaela Nyerges, Partener - Vlăsceanu, Nyerges & Partners

The practice of the authorities seems to differ: there are local authorities that request a PUZ for the issuance of the building permit, and authorities that no longer impose such an obligation through the urban planning certificate.

 
 

One of the most frequent questions asked there days by renewables investors and developers is whether PUZ is still required for developing small renewable power projects in Romania (below 50 ha). The relevance of this question is huge as the answer impacts on the duration of the development process with up to 9 months.

To answer, brief preliminary comments should be made regarding the general construction permitting rules, depending on the various types of lands.

1.          Types of lands

The following lands qualifications are relevant for the current topic:

(i)         from the perspective of their location, the lands can be (a) located intra-muros (within the buildable perimeter of the respective territorial administrative unit) or (b) located extra-muros (outside such perimeter);

(ii)       from the perspective of their destination, the lands can be, among others, (a) agricultural lands or (b) yards-constructions lands;

(iii)      from the perspective of their fertility class, the agricultural lands are split into 5 fertility classes, ranging from very fertile land (Class I) to very low fertile land (Class V); the fertility class is established based soil analysis made by experts within the county Office of Pedological Studies.

2.          General construction rule

As a general rule, all constructions may be erected only on lands (i) located intra-muros and (ii) qualifying as “yards-constructions”.

If the targeted land qualifies as extra-muros and agricultural land (which is typically the case with the land suitable for renewable projects),

(i)         the land should be first requalified from extra-muros into intra-muros land by means of a PUZ;

(ii)       no additional formalities should be done for converting the land from agricultural land to “yards-construction” land, as such conversion occurs automatically through the issuance of the building permit.

3.          Exception dedicated to renewable energy projects

Late July this year, an exception from the above rule was adopted, expressly allowing the construction of renewable power generation projects on extra-murros lands if the following conditions are met:

(i)         land has fertility class III, IV and V; and

(ii)       land does not exceed 50 ha.

Therefore, projects falling within the above limitations no longer need to obtain requalification of the land from extra-muros to intra-murros land through a PUZ.

4.          Need of a PUZ in case of renewable projects below 50 ha

Therefore, do we still need or not a PUZ for developing renewable on land with fertility class III, IV and V which does not exceeds 50 ha?

The practice of the authorities seems to differ: there are local authorities that request a PUZ for the issuance of the building permit, and authorities that no longer impose such an obligation through the urban planning certificate. We have also encountered a case where the authority changed its mind after having issued an urban planning certificate whereby no PUZ was requested.

Nevertheless, it should be mentioned that PUZ has multiple roles, not just the introduction of land into intra-murros area, as explained below:

(i)            according to the general construction law (with certain exceptions not applicable hereto), the building permit may be issued only if (a) there is an urban documentation approved regarding the respective land, setting out the legal, technical and economical regime of the land and (b) the envisaged construction is compatible with the rules set out by the respective urban documentation;

(ii)          all communes and towns in Romania must have an urban documentation approved – namely a general urban plan (“PUG”) adopted by the local authorities setting out (a) the function of each land (such as residential, industrial etc.) and (b) the applicable urbanism parameters and limitations (such as land occupation percentage, land occupation coefficient, height regime, etc.);

(iii)        PUG is a sufficient urbanism documentation for the issuance of a building permit if (a) it provides the legal, technical and economical regime of the targeted land and (b) the envisaged project is compatible with the regime set out thereby;

(iv)        if (a) the PUG does not provide the legal, technical and economical regime of the targeted land or (b) the envisaged construction is not compatible with the rules set out by the PUG for the targeted land or (c) there is no PUG in place (for example, it was never approved, it expired, it was cancelled in court or suspended), the developer must obtain a zonal urban plan (“PUZ”) whereby to adopt/amend the urbanism rules so that they are compatible with the project;

(v)          generally, PUGs do not regulate extra-muros land or do not establish an urbanism function/regime compatible with renewable projects;

(vi)        very recently, a new exception from the need to adopt an urbanism documentation was added in case of other specific types of constructions allowed on extra murros land.

Further to the above, PUZs are still needed for developing renewable projects on lands below 50 ha in order to establish the function and urbanism parameters of the respective land that are compatible with the envisaged project. Nevertheless, a case-by-case assessment should be made regarding the PUG rules applicable on the respective land. Such assessment should be made by the consultants of the developer, without simply relying on the assessment made by the local authorities when issuing the urbanism certificate.

 
 

PNSA

 
 

ARTICOLE PE ACEEASI TEMA

ARTICOLE DE ACELASI AUTOR


 

Ascunde Reclama
 
 

POSTEAZA UN COMENTARIU


Nume *
Email (nu va fi publicat) *
Comentariu *
Cod de securitate*







* campuri obligatorii


Articol 743 / 4382
 

Ascunde Reclama
 
BREAKING NEWS
ESENTIAL
Mergermarket - League Tables of Legal Advisors (Q3 2024) | Piața de M&A a continuat să se redreseze în primele nouă luni și a înregistrat creșteri de 18,8% la nivel global și de 23% în Europa. CMS, printre primele în clasamentul global și în Europa. Schoenherr și Wolf Theiss, număr mare de tranzacții asistate în Europa Centrală și de Est
LegiTeam: Lawyer - Corporate M&A | Reff & Associates
UniCredit Bank a încheiat cu succes cea mai mare emisiune a sa pe piaţa locală de obligațiuni corporative negarantate, în valoare de 750 mil. lei. Clifford Chance Badea a asigurat consultanța juridică
Cine sunt și cum gândesc profesioniștii evidențiați de Legal 500 în GC Powerlist Romania | De vorbă cu Laura Rudnyanszky, Global Regulatory Lead – Accenture, profesionist al Dreptului antrenat în proiecte complexe, care coordonează azi o echipă de avocați în reglementări globale: ”În carieră, îmi respect clienții și echipa, tratând fiecare provocare cu profesionalism și empatie. Aspirația mea este să ocup o poziție de conducere în cadrul unei organizații care valorizează inovația și responsabilitatea socială, unde să pot influența pozitiv modul în care se practică dreptul și cum se integrează tehnologia în procesele juridice”
Meet the Professionals | Din vorbă în vorbă cu Andreea Zvâc, proaspăt promovată Partner în cadrul firmei Wolf Theiss, despre mediul în care s-a împlinit profesional, implicare și valori: “În avocatură ai posibilitatea de a fi creativ și nu te plictisești niciodată. Pentru o evoluție sustenabilă și coerentă a unui avocat, munca și pasiunea ar trebui să fie pe primul loc”
(VIDEO) INTERVIURI ESENȚIALE | Horea Popescu, Managing Partner CMS România: ”Am avut privilegiul de a fi implicați în câteva dintre tranzacțiile esențiale din economie. Cifrele arată foarte bine, am învățat ce trebuie să facem pentru a merge odată cu curentul, dar și împotriva acestuia, când este cazul”
BeeFast primește o nouă finanțare în valoare de 450.000 USD pentru extinderea internațională și dezvoltare. Avocații Baciu Partners, în tranzacție, cu o echipă coordonată de Corina Roman (Partener)
LegiTeam | MITEL & ASOCIAȚII recrutează avocat cu experiență (Real Estate)
LegiTeam: Voicu & Asociații is looking for business lawyers
2024 a fost un an aglomerat pentru Departamentul juridic al Farmexim & Help Net | De vorbă cu Mihaela Scărlătescu, Head of Legal and Compliance Director despre actele normative cu impact în activitatea companiei, modificările legislative așteptate și proiectele interesante în care a fost implicată echipa de avocați interni
GDPR | Echipa Mitel & Asociații a fost implicată în mai multe proiecte complexe, printre cele mai solicitante fiind cele legate de tranzacții de tip M&A, dezvoltarea unor aplicații și implementarea unor soluții de conformitate la scară largă, în industrii cu volume mari de date cu caracter personal. Mădălina Mitel, Partener: ”Anticipăm o creștere semnificativă a cererii pentru servicii de consultanță în domenii emergente precum AI, procese automatizate și date biometrice, pe măsură ce reglementările devin mai stricte și aplicarea normelor devine mai riguroasă”
Cine sunt și cum gândesc profesioniștii evidențiați de Legal 500 în GC Powerlist Romania | De vorbă cu Iulian Gânju, Head of Legal - Iulius Group: „Mi-a plăcut foarte mult această zonă de ‘in-house’ deoarece presupune o centrare pe respectarea legislației și corectitudine în procesele de business, idee care rezonează foarte mult și cu principiile și valorile la care mă raportez în fiecare zi”
 
Citeste pe SeeNews Digital Network
  • BizBanker

  • BizLeader

      in curand...
  • SeeNews

    in curand...