CMS | Romania shifts towards auction-based mechanism for grid access

06 August 2024   |   CMS Romania

For more information on Romania’s new auction-based system for grid access, contact your CMS client partner or these CMS experts: Varinia Radu and Raluca Diaconeasa.

 
 
On 2 August 2024, Romania’s National Energy Regulatory Authority (ANRE) published an order stating that access to Romania’s power grid will change to an auction-based mechanism in 2026. The order replaces the current mechanism for allocating grid capacity based on auctions, which has obliged grid connection applicants to participate in general reinforcement works for the electricity grid upstream of the connection point. Through the proposed auction-based capacity allocation mechanism, grid operators will use the amounts collected for electricity-grid development.

The new mechanism, which will be applicable on 1 January 2026, will do the following:

→    Connect new production/consumption and production sites with or without storage installations with electricity generation installations of 5 MW or more and new storage installations of 5 MW or more;

→    Allocate additional power when placing additional installations for electricity generation/storage of 5 MW or more at an existing production/consumption site;
→    Connect existing consumption sites with installations for electricity generation/storage of 5 MW or more.

According to the order, the auctions will be held annually for tenders of ten years. The following is the envisaged calendar of auctions:

→    Until 15 January: publication by the national Transmission System Operator (TSO) of the available grid capacity;
→    16 January – 28/29 February: submission of capacity applications;
→    1 March – 10 March: Distribution Grid Operators (DSO) transmit requests for capacity allocation to the TSO;
→    Until 15 March: the TSO finalises the list of applications;
→    16 March – 15 June: the TSO conducts a global solution study determining the necessary grid reinforcement works for all capacity applications;
→    Until 15 June: the TSO publishes the conclusions of the global solution study, available grid capacity, auctioning price and date for each bidding session;
→    Starting 1 July: bidding sessions will be held daily for allocating available capacity. The bidders will be able to place bids for capacity for one year (of the tendered ten-year period).

Auction particularities

The TSO will address requests for capacity allocation for generation sites with installed capacity greater than 50 MW and to the relevant DSO for generation sites with installed capacity up to and including 50 MW. The year requested for the capacity allocation will correspond to the year of the commissioning of the utilisation installations at the generating site.

The starting price of the auction will be determined by referring the total estimated value of the reinforcement works to the total grid capacity available for allocation, including capacity resulting from reinforcement works. The offers will be ranked from the highest bidding price.

The applicants must submit a bid bond determined by multiplying the capacity requested by a bidder, expressed in MW, by 1% of the starting price of the auction.

Depending on the level of competition, these are the possible scenarios:

→    If the sum of the requested capacity is less than or equal to the available capacity for grid connection, then all bids will be accepted. In this case, the auction session for the allocation of available capacity will not take place.
→    If the sum of the requested capacity is higher than the available capacity, without the capacity from additional development works, but is less than the available capacity including the capacity from additional development works, the auction will be conducted and all bids will be accepted in full until awarding the capacity available for connection.
→    If the sum of the requested capacity is higher than the available capacity including the capacity from additional development works, the auction will be conducted and all bids will be accepted in full until awarding all the capacity available for connection.
→    If the sum of the requested capacity is greater than the available capacity, which does not include the capacity from additional development works, the auction will be conducted considering the value of additional development works from the first year of the allocation period following that of the current auction. All bids will be accepted in full until all the capacity available for connection is awarded.

For each successful bid, the user must pay the tendered price. The first unsuccessful bid will be the bid with the highest price among the unsuccessful bids. In this case, if there is available capacity, the bidder may choose:

→    to secure the necessary grid capacity with commissioning in the year following the year for which he initially opted, by concluding the allocation contract and paying the tendered price;
→    not to secure the grid capacity for the following year, but to participate in the bidding session for the allocation of available capacity in the year following the year for which he initially opted;
→    to withdraw the request for grid capacity allocation.

Successful bidders will enter capacity allocation contracts with the relevant grid operator.

Capacity allocation contracts

Within five days from the auction date, the TSO will issue the capacity allocation contracts. The successful bidder is obliged to provide financial security equal to 1% of the value of the contract upon concluding the contract.

The mandatory clauses of the capacity allocation contracts are presented in the draft order as an annex to the auction methodology.

In principle, the capacity allocation contract provides for the capacity allocated to the applicant and the amount to be paid for that capacity, determined by multiplying the allocated capacity by the auction price. The applicant is obliged to pay the above-mentioned amount within four months from the signing date of the contract. The amount will be paid in instalments. The first instalment will represent at least 20% of the amount of the allocated capacity and will be paid no later than 30 days after the signing date of the contract.

The capacity allocation contract also provides for bilateral penalties. If network operators won’t bring into operation the installations resulting from reinforcement works within the applicable deadlines, they will be obliged to pay the users who have incurred the costs of those works a percentage of 0.01% per day of delay, applied to the value paid by the user for the allocated capacity until the necessary capacity allocated by tender has been secured. The same penalty is applied to users who do not meet the deadline for the final energisation of the production/consumption and production site.

Importantly, capacity allocation contracts can be assigned in whole or in part with the prior consent of the other party.

Changes in the financial guarantee’s regime

Apart from the capacity allocation system, the draft order also brings changes to the financial guarantee requested by the grid connection permit (ATR).  Until recently, the financial guarantee was up to 20% of the grid connection tariff and was only required in cases where reinforcement works were needed. In addition, the previous legal regime requested the financial guarantee to be submitted until the conclusion of the grid connection agreement.

In contrast, according to the new order, there is an obligation for all applicants to constitute a financial guarantee, regardless of the existence of an obligation to provide for reinforcement works. In addition, the level of the financial guarantee has been established to a fix amount of 5% of the feed-in tariff. Where reinforcement works are not needed, the obligation to provide the financial guarantee is due before the ATR’s date of issue, and where reinforcement works are needed, the financial guarantee is must be provided within the deadline specified in the grid connection contract.

These amendments will apply to requests for connection of the users for which, by the date of entry into force of the order, the ATR has not been issued.

Conclusions

The new auction-based mechanism is expected to create a competitive environment that provides predictability for the development of energy sources in the energy system. According to ANRE representatives, the importance of the auction mechanism is the possibility for applicants to secure the necessary capacity for subsequent connection to the grid. In addition, the new mechanism will secure for network operators the necessary amounts for the implementation of additional work required to develop the power grid to connect new generation sites.

For more information on Romania’s new auction-based system for grid access, contact your CMS client partner or these CMS experts: Varinia Radu and Raluca Diaconeasa.

This article has been co-authored by Ada Romanti, Lawyer at CMS.

 
 

PNSA

 
 

ARTICOLE PE ACEEASI TEMA

ARTICOLE DE ACELASI AUTOR


 

Ascunde Reclama
 
 

POSTEAZA UN COMENTARIU


Nume *
Email (nu va fi publicat) *
Comentariu *
Cod de securitate*







* campuri obligatorii


Articol 64 / 4378
 

Ascunde Reclama
 
BREAKING NEWS
ESENTIAL
Cele mai semnificative schimbări legislative din 2024, cu impact în industria curieratului | Cerasela Soviani, Legal Manager în cadrul DPD Romania: ”Departamentul juridic va avea un focus continuu pe respectarea noilor reglementări în curierat și susținerea departamentelor pilon pentru extinderea rețelei naționale”
LegiTeam | MITEL & ASOCIAȚII recrutează avocat cu experiență (Real Estate)
GDPR | Respectarea legislației în domeniu pare că este mai degrabă formală, lipsind măsurile concrete capabile să asigure o protecție adecvată volumului foarte mare de date prelucrate, spun avocații D&B David și Baias. Daniel Vinerean, coordonatorul practicii de Protecția Datelor: De cele mai multe ori este mai ieftin sa plătești o amendă de până la 3.000 € decât să stabilești un plan concret, să achiziționezi tehnologie sau să angajezi un consultant capabil să conceapă și să implementeze măsuri adecvate
ZRVP câștigă premiul „Firma de Avocatură a Anului din România” la Lexology Index Awards (Who’s Who Legal) 2024, distincție acordată în premieră unei societăți de avocați românești | Cosmin Vasile (managing partner): Premiul, o sumă a excelenței individuale pe diverse arii de practică - îmi place în mod special perspectiva, pentru că este exact filosofia noastră
Schoenherr lansează a patra ediție a concursului de eseuri „law, sweet law‟, cu premii totale de 18.000 lei
Decizie de referință în domeniul energiei regenerabile: Curtea Constituțională admite sesizarea de neconstituționalitate referitoare la supraimpozitarea producătorilor de energie din surse regenerabile
Studenții invitați să se alăture programului de internship oferit de Schoenherr au derulat stagii de practică cu perioadă flexibilă, personalizată atât în funcție de programul lor, cât și de nevoile firmei de avocați | Ana Lupșor, HR manager: „Am avut o vară intensă, cu multe activități desfășurate în comun. Studenții au luat contact nu doar cu activitatea profesională ca avocat într-o firmă internațională de avocatură de afaceri, ci și cu spiritul și cultura echipei Schoenherr”
NNDKP CELF, o nouă soluție de recunoaștere în instanță a dreptului de deducere a TVA aferente cheltuielilor de investiție în cazul abandonului proiectului | Alexandru Aparaschivei (Partener NNDKP CF), Marius Ezer (Partener) și Florentin Nanu (Avocat Senior), în prim plan
Victorie importantă, ce consolidează principiul libertății activității politice | Popescu & Asociații obține achitarea definitivă pentru membrii PNL Timiș, Cosmin Șandru și Nicolae Bitea. Echipa, coordonată de Adrian CHIRVASE (Partner) și Mirel RĂDESCU (Senior Counsel)
Cariere în Drept | De vorbă cu Ramona Andreea Stoica, printre primii absolvenți ai generației care și-a finalizat studiile în 2023, urmărind mai apoi o carieră în magistratură: ”Dreptul este un domeniu frumos, pe care trebuie uneori să ‘îl simți’, însă nu este pentru toți. Cred că media a fost doar o reflectare a efortului depus, iar efortul a fost cel care m-a ajutat și mi-a creat premisele evoluției profesionale ulterioare”
Arbitrajul ICSID cerut de Petrochemical Holding GmbH, legat de rafinări RAFO din Onești, a ajuns la final | Statul român așteaptă decizia, după ce Tribunalul a declarat închisă procedura în litigiul în care pretențiile se ridică la cca. 836 milioane USD. Ce onorarii au fost plătite firmelor de avocați care au asigurat apărarea
2024 a fost un an aglomerat pentru Departamentul juridic al Farmexim & Help Net | De vorbă cu Mihaela Scărlătescu, Head of Legal and Compliance Director despre actele normative cu impact în activitatea companiei, modificările legislative așteptate și proiectele interesante în care a fost implicată echipa de avocați interni
 
Citeste pe SeeNews Digital Network
  • BizBanker

  • BizLeader

      in curand...
  • SeeNews

    in curand...