Kinstellar | Joint study of the Romanian Competition Council and Romanian Energy Regulatory Authority identifies barriers to market entry for renewables producers and issues recommendations

09 Octombrie 2023   |   Iustinian Captariu (partner) and Catalin Graure (Managing Associate) - Kinstellar

Roughly two months after publishing the preliminary conclusions following its study on permitting bottlenecks in the renewables sector (that we wrote about here), the RCC has now teamed up with the Romanian Energy Regulatory Authority (ANRE), in a joint effort to assess grid access and barriers thereto. This point particularly had been one of the thorniest aspects for developing new power generation capacities in Romania.

Iustinian Captariu (partner) and Catalin Graure (Managing Associate) - Kinstellar

 
 
The Romanian Competition Council (RCC) continued focusing on the energy markets, not only though investigations or merger control analysis, but also by carefully reviewing the markets through sector inquiries and studies. Given Romania’s declared interest into considerably bolstering its renewables capacities on the short term, also backed up by EU funds and the Contracts for Difference (CfD) support scheme in the pipeline, renewables have been high on the RCC’s agenda recently.

Roughly two months after publishing the preliminary conclusions following its study on permitting bottlenecks in the renewables sector (that we wrote about here), the RCC has now teamed up with the Romanian Energy Regulatory Authority (ANRE), in a joint effort to assess grid access and barriers thereto. This point particularly had been one of the thorniest aspects for developing new power generation capacities in Romania.


In brief, some of the main points and recommendations highlighted by the preliminary report published yesterday include:
    barriers to grid access include the lack of disincentives against speculative investments. The study identifies a market practice of developers only getting projects at ‘ready to build’ to further sell them to other developers. This is considered speculative, as potentially leading to blocking some more credible investments, as new grid connection permits (ATR) would be very difficult to obtain while previously issued ATRs are valid and many of the ‘speculative’ projects eventually end up abandoned – suggested deterrents against speculators may include setting up execution guarantees or sanctioning developers’ passivity over extended periods;

→    the grid connection process is lengthy because of the legislation which is unclear or uncorrelated in some respects – grid connection regulations should be further clarified and the authorities suggest implementing a “one-stop-shop” contact point for obtaining a single license for RES production, with representatives from the public administration and the network operators; 
→    financing-related barriers are mostly related to prohibitive grid reinforcement costs (with tariffs of about EUR 100,000/MW);
→    the power transmission and distribution networks are underdeveloped and previously approved development plans had difficulties in being implemented (due generally by the duration in ticking the boxes on public procurement, works execution, government decisions and environmental permitting, missing cadastral plans) – putting together a strategy on dealing with congestions and placing new generation capacities should be considered by the Ministry of Energy and relevant authorities;
→    the suggestion of allocating grid connection capacities based on competitive procedures, carried out periodically, depending on grid development;
→    the need of further qualification for the various experts and personnel involved in the process, both on the distribution operators and developers’ consultants’ side;

A full Romanian language copy of the joint RCC-ANRE report is available here and the authorities await comments from interested parties by 4 November 2023.

 
 

PNSA

 
 

ARTICOLE PE ACEEASI TEMA

    ARTICOLE DE ACELASI AUTOR


       

      Ascunde Reclama
       
       

      POSTEAZA UN COMENTARIU


      Nume *
      Email (nu va fi publicat) *
      Comentariu *
      Cod de securitate*







      * campuri obligatorii


      Articol 558 / 4654
       

      Ascunde Reclama
       
      BREAKING NEWS
      ESENTIAL
      Echipele reunite Peligrad Law și David & Baias obțin o hotărâre de referința a Tribunalului Uniunii Europene privind încadrarea tarifara a băuturii tip cidru, marca Strongbow, care confirma ca nivelul accizei pentru această băutură este zero
      LegiTeam: CMS CAMERON MCKENNA NABARRO OLSWANG LLP SCP is looking for: Associate | Commercial group (3-4 years definitive ̸ qualified lawyer)
      Remontada și victorie definitivă în fața Curții de Apel Ploiești pentru echipa de litigii fiscale a RTPR pentru Rosti Romania SRL | Ajustarea pierderii fiscale efectuată prin estimare considerată nelegală; dosarul prețurilor de transfer necontestat de organele fiscale trebuie avut în vedere
      Bohâlțeanu & Asociații a asistat Premier Energy, jucător major în sectorul energetic, într-o cascadă de tranzacții în care a fost cumpărător și vânzător. Proiect multijurisdicțional complex, executat de o echipă pluridisciplinară, coordonată de Ionuț Bohâlțeanu (Managing Partner)
      Țuca Zbârcea & Asociații asistă Omnia Capital B.V. într-o suită de tranzacții complexe pe piața de energie din România. Avocați cu senioritate înaltă, în echipa pluridisciplinară
      România a pierdut arbitrajul ICSID cerut de mai mulți dezvoltatori de parcuri fotovoltaice. Comitetul ad-hoc format din trei arbitri a respins cererea de anulare a hotărârii Tribunalului prin care statul român a fost obligat să plătească peste 40 mil. € | Reclamanții au mers cu King & Spalding (Houston și Paris), apărarea a fost asigurată de o firmă americană și una locală
      Exim Banca Românească, parte a consorțiului internațional de bănci care finanțează Ogrezeni, unul dintre cele mai mari proiecte hibride din Europa, cu 460 mil. € | Schoenherr și Clifford Chance Badea, în tranzacție
      BERD, CEECAT Capital și Morphosis Capital își marchează exitul din investiția în La Cocoș. Osborne Clarke, Van Campen Liem și Noerr, în tranzacție, alături de trei firme locale de avocați
      Popescu & Asociații rămâne un reper de seriozitate și profunzime, cu o cultură care privilegiază calitatea, consecvența și responsabilitatea | De vorbă cu Adrian Chirvase (Partener) despre 2025 ca an de consolidare: portofoliu diversificat, retenție ridicată, tehnologie folosită pragmatic și o echipă unită, pregătită pentru mandate transfrontaliere
      Filip & Company a asistat Veranda Obor S.A. în obținerea unei finanțări de 36 milioane euro de la CEC Bank. Echipa, coordonată de Alexandra Manciulea (partner) și Rebecca Marina (counsel)
      O promovare din interior care confirmă meritocrația și creșterea organică într-una dintre cele mai puternice firme de avocatură din România | De vorbă cu Ramona Pentilescu, avocatul care a crescut în PNSA de la primii pași în profesie până la poziția de partener, despre vocație, rigoare și reperele care i-au susținut evoluția profesională într-un cadru în care contează respectul pentru profesie și coerența valorilor
      Neagu Dinu Partners, firmă înființată anul trecut, își face rapid loc în prim-planul practicii de Litigii & Arbitraj din piața locală, cu un model de lucru pragmatic, în care partenerii cooordonează dosarele și păstrează controlul calității în mandate complexe | De vorbă cu Simona Neagu (Partener fondator) despre așteptările tot mai ridicate ale clienților, colaborările internaționale și disciplina internă care susține performanța echipei
       
      Citeste pe SeeNews Digital Network
      • BizBanker

      • BizLeader

          in curand...
      • SeeNews

        in curand...