On 1 January 2026, Romania enforced ANRE Order 83/2025, which amends the process for granting authorisations and licences in the natural gas sector and repeals the previous 2020 Regulation.

The following article summarises the most important updates and explores their potential impact.
Removal of authorisation for liquefied natural gas (LNG) and hydrogen installations

The new regulation removes setting-up authorisations for LNG and hydrogen production sites. Licences can still be obtained for LNG supply and the operation of LNG terminals, and for the commercial exploitation of hydrogen production installations. As a result, LNG and hydrogen projects licensing is expected to be more straightforward in comparison to the 2020 Regulation.


New requirements for supply and trading licences

To obtain supply or trading licences, applicants must file evidence of financial resources of at least EUR 200,000 (or its equivalent) as opposed to the previous Regulation, which required financial resources of 25% of the estimated turnover to be achieved in the first 12 months of activity, but not less than EUR 100,000. Similarly, the request will require the proof of effective employment contracts for at least three employees, each with a minimum of three years prior experience in the natural gas sector.

ANRE also requires current licence holders to provide the same evidence, along with a list of Romanian locations where the activity will be conducted and a list of single points of contact for informing end customers, within a maximum of six months from the date of approval of this regulation. This means that supply and trading licence holders have until 1 June 2026 to submit proof of compliance with the new provisions.

Changes in duration and extension of setting-up authorisations and licences

According to the changes, supply and trading licences now have an initial duration of up to five years. The overall maximum duration of 25 years remains unchanged and continues to apply to all other categories of licences.

If the minimum 30-day deadline for filing an extension request is missed or if the documentation remains incomplete by the date of expiry of the setting-up authorisation or licence, the request is treated as an application for a new setting-up authorisation for the remaining investment or for a new licence. This creates a clear procedural distinction that did not exist in 2020.

Furthermore, upon expiry of the maximum validity period, holders may apply for a new setting-up authorisation or a new licence, provided they do so at least 90 days before expiry. For infrastructure operating licences (i.e. upstream pipelines, storage, transmission, distribution), the duration of the new licence is tied to the term of the “new contracts” underpinning the activity (e.g. new concessions), thereby formalising automatic recalibration to the contractual basis.

Changes in the application file analysis term for licences

Another clear procedural distinction to the previous regulation is the 60-day term of license granting file analysis as opposed to the previous 30-day term.

Upon analysis of the file, the applicant has 60 days to respond to the observations and additional requests from ANRE as opposed to the previous 30-day term.

The six months overall limitation period for the file review of applications remains the same. What is new is that the respective six-month term may be extended when ANRE is conducting an audit in connection with the application of the respective company.

Removal of the requirement to pay upfront

The changes remove upfront payment upon request being filed to a date following ANRE assessment of the documentation. Previously, applicants were required to submit proof of payment of the analysis tariff together with the filing. Failure to pay within ten business days resulted in ANRE not analysing the request.

Licensing requirement for foreign operators without home-state licensing systems

Where the energy regulatory authority or another competent authority in the operator’s member state does not issue licences or similar documents allowing natural gas supply or natural gas trading, an economic operator wishing to conduct natural gas supply or trading in Romania must obtain a Romanian natural gas supply or trading licence under this regulation, and maintain a physical point of contact in Romania for the entire licence term.

Under the 2020 Regulation, EU-established operators from EU member states that lacked a similar licencing regime but had the equivalent certification for trading or supply activity in their home state could participate in the Romanian market on the basis of an ANRE confirmation without needing a separate Romanian licence or an active local legal presence. The new amendment removes the previous facility and expressly imposes specific Romanian licencing requirements even for well-versed traders active in multiple member states that do not have a similar licensing regime, making the licence passporting process more restrictive to implement.

Operators established in member states where a comparable licencing regime exists can still participate in the Romanian gas market on the basis of confirmation by ANRE that they hold a home-state licence.

Annual GIS reporting obligations

Holders must submit, annually by the end of March, updated GIS information for all targets in operation on 1 March of that year. The regulation further clarifies that this obligation also applies to licences obtained after 31 January 2021.

Under the 2020 Regulation, GIS data were required as a one-off submission for all operating assets by 31 January 2021, rather than as an ongoing annual update duty.

New withdrawal grounds and enforcement measures

ANRE introduces two additional punitive situations with clear disciplinary purpose, which trigger licence withdrawal:

→    non-payment of amounts owed to ANRE or the inability to reach the holder for payment within one year of invoice issuance, in which case the licence may be withdrawn without prior notice; and
→    breach by the supplier of the prohibition in Law 123/2012 by sending unilateral termination notices to end customers.

These specific grounds for license withdrawal were not previously listed in the 2020 Regulation.

For more information on how the new regulations that came into force on 1 January will affect your Romania-based business, contact your CMS client partner or the CMS experts who contributed to this article: Varinia Radu, Ramona Dulamea, Raluca Diaconeasa and Madalina Constantinescu.
 
 

PNSA

 
 

ARTICOLE PE ACEEASI TEMA

ARTICOLE DE ACELASI AUTOR


     

    Ascunde Reclama
     
     

    POSTEAZA UN COMENTARIU


    Nume *
    Email (nu va fi publicat) *
    Comentariu *
    Cod de securitate*







    * campuri obligatorii


    Articol 41 / 4669
     

    Ascunde Reclama
    BREAKING NEWS
    ESENTIAL
    Un nou front juridic la Washington | Forty Management AG acționează România în judecată la ICSID. Schoenherr (Viena) și Daniel F. Visoiu sunt alături de reclamanți în acest arbitraj în care România este reprezentată printr-o structură instituțională complexă, care include și Banca Națională a României, într-o notă ce sugerează implicații financiare sau monetare deosebite
    LegiTeam: Reff & Associates is looking for a 3 - 6 years Attorney at Law | Dispute Resolution
    Eșec de strategie juridică sau impas suveran? România, sancționată repetat în SUA pentru că ascunde activele ce pot fi executate de familia Micula. Săptămâna aceasta a fost obligată la plata unei amenzi noi, de 5,8 milioane de dolari, ridicând totalul penalităților la 21 milioane de dolari | Cazul Micula vs România a devenit „pacientul zero” într-o dezbatere juridică amplă care vizează arhitectura tratatelor de investiții în interiorul Uniunii Europene
    RTPR obține definitiv peste 1,7 mil. € pentru un client din zona ONG, în urma anulării a 80 de contracte de vânzare într-un litigiu de proprietate cu peste 90 de pârâți | Alexandru Stănoiu (Counsel) și Șerban Nițulescu (Associate), în prim plan
    România a câștigat arbitrajul ICSID cu Plaza Centers N.V. pentru Casa Radio și a scăpat de pretenții de 425 mil. €. Reclamanții rămân cu arbitrajul comercial inițiat la Londra de Ministerul Finanțelor, în care pretențiile României sunt de circa 2 miliarde €
    Studiu LSEG Data & Analytics Q1 2026 | Piața globală de M&A a crescut cu 27% în primul trimestru, cu un avans spectaculos în Europa, unde a atins maximul ultimilor opt ani. CMS și DLA Piper continuă să stralucească în topul global al consultanților juridici, Clifford Chance și Schoenherr rămân active în clasamentele continentale, iar în Top 20 Europa de Est sunt vizibile doar două firme cu birou la București
    Bondoc & Asociații anunță 10 promovări, inclusiv un nou Partener | Lucian Bondoc (Managing Partner): ”Firma va continua să urmeze aceeași abordare, în care recunoașterea meritocratică și echitabilă a expertizei și a contribuției la obiectivele noastre comune joacă un rol esențial”
    LegiTeam - Oportunitate de carieră | Avocat definitiv – Achiziții publice & Infrastructură
    LegiTeam: Zamfirescu Racoţi Vasile & Partners recrutează avocat definitiv Dreptul muncii | Consultanță
    O nouă serie de promovări la biroul Kinstellar din București. Șapte avocați din mai multe arii de practică fac un pas înainte în carieră. Theodor Artenie urcă pe poziția de Partner, iar Lidia Zărnescu și Răzvan Constantinescu devin Counsels | Iustinian Captariu, Office Managing Partner: ”Forța biroului nostru vine din talentul, colaborarea și angajamentul comun al întregii echipe”
    Legiteam | Kinstellar is looking for a talented and ambitious lawyer to be part of our employment team in Bucharest
    Filip & Company asistă Grupul DIGI Communications la intrarea pe piața telecomunicațiilor din Regatul Unit | Echipa, coordonată de Alexandru Bîrsan (managing partener)
     
    Citeste pe SeeNews Digital Network
    • BizBanker

    • BizLeader

        in curand...
    • SeeNews

      in curand...