IP Right Enforcement in the EU: CJEU Reduces Claimant’s Liability Risk when Seeking Preliminary Injunctions
18 Noiembrie 2019 Schoenherr
The result of the decision, however, raises the question of whether national laws comply with the requirements of the Enforcement Directive as interpreted by the CJEU in the Bayer Pharma decision.
The Court of Justice of the EU (CJEU) recently dealt with "appropriate compensation" due in cases where a preliminary injunction based on IP rights was lifted or not rectified in subsequent main proceedings.
Compensation for unjustified preliminary measures under EU law
Case C-688/17, Bayer Pharma, concerned questions for a preliminary ruling brought by a Hungarian court in patent infringement proceedings. In these proceedings the court issued preliminary injunctions, which were finally revoked due to the invalidity of the patent. The successful defendants therefore subsequently claimed compensation for losses incurred due to the apparently unjustified preliminary injunction.
In its decision, the CJEU states that "appropriate" (a term used in Article 9(7) of the EU Enforcement Directive aimed at facilitating enforcement of IP rights) as a concept of EU law must be given an independent and uniform interpretation in all EU Member States and that an assessment of whether damages are "appropriate" must take into account the overall circumstances of each case. The courts are therefore not automatically and not in every case obliged to grant compensation for damages if a preliminary injunction is subsequently not rectified, but "only in the case of an unjustified application". The CJEU links the answer to the question of whether an application was "unjustified" not only to the objective circumstance that the preliminary injunction could not be rectified in the subsequent main proceedings. It even requires on the subjective side that the application was filed "abusively". Otherwise, the IP right holders could be deterred from applying for preliminary measures at all, which would contradict the Enforcement Directive's objective of ensuring a high, equivalent and homogeneous level of protection for intellectual property (including industrial property rights).
Compensation for unjustified preliminary measures under EU law
Case C-688/17, Bayer Pharma, concerned questions for a preliminary ruling brought by a Hungarian court in patent infringement proceedings. In these proceedings the court issued preliminary injunctions, which were finally revoked due to the invalidity of the patent. The successful defendants therefore subsequently claimed compensation for losses incurred due to the apparently unjustified preliminary injunction.
In its decision, the CJEU states that "appropriate" (a term used in Article 9(7) of the EU Enforcement Directive aimed at facilitating enforcement of IP rights) as a concept of EU law must be given an independent and uniform interpretation in all EU Member States and that an assessment of whether damages are "appropriate" must take into account the overall circumstances of each case. The courts are therefore not automatically and not in every case obliged to grant compensation for damages if a preliminary injunction is subsequently not rectified, but "only in the case of an unjustified application". The CJEU links the answer to the question of whether an application was "unjustified" not only to the objective circumstance that the preliminary injunction could not be rectified in the subsequent main proceedings. It even requires on the subjective side that the application was filed "abusively". Otherwise, the IP right holders could be deterred from applying for preliminary measures at all, which would contradict the Enforcement Directive's objective of ensuring a high, equivalent and homogeneous level of protection for intellectual property (including industrial property rights).
Impact on national laws
The result of the decision, however, raises the question of whether national laws comply with the requirements of the Enforcement Directive as interpreted by the CJEU in the Bayer Pharma decision.
For example, the national legislation in Hungary (as enshrined by the decision of the CJEU) permits the court to take due account of the negligence or fault of both the party applying for the preliminary injunction and the defendant. Although the provisions of the old Civil Code (Act IV of 1959) assessed by the CJEU have been replaced in the meantime by the new Civil Code (Act V of 2013), the substance of the new rules remains unchanged. The injured party is obliged to act as would generally be expected in the circumstances in question to avoid or to mitigate the loss. The injured party will not be compensated for loss resulting from its failure to comply with this obligation. These provisions are a double-edged sword resulting in the conduct of both parties being assessed on a case-by-case basis, i.e. whether the applicant applied for the preliminary injunction abusively, and whether the party suffering loss from such an injunction indeed did what was expected to avoid the loss (e.g. by not marketing the product before the conclusion of the patent invalidity proceedings). In the CJEU's view this national legislation should be in line with the objectives of the Enforcement Directive.
On the other hand, Section 394 of the Austrian Enforcement Act (Exekutionsordnung) foresees strict liability for damages caused by unrectified preliminary injunctions regardless of negligence or fault, which no longer seems to be in line with the findings of the CJEU.
The CJEU thus brought some clarity to the EU-wide interpretation of the Enforcement Directive, certainly decreasing the risk for IP owners to enforce their rights via preliminary measures in the EU. However, important questions still need to be resolved by the national courts (or even the CJEU in subsequent proceedings). Particularly which circumstances would qualify as "abusive" pursuant to the CJEU but also the applicability in proceedings other than those directly dealing with the enforcement of registered IP rights (i.e. unfair competition claims, trade secret protection, etc.) seems to provide some room for future discussion.
| Publicitate pe BizLawyer? |
![]() ![]() |
| Articol 4509 / 4685 | Următorul articol |
| Publicitate pe BizLawyer? |
![]() |
BREAKING NEWS
ESENTIAL
Mușat & Asociații obține o decizie de referință pentru salariații Hidroconstrucția, societate în reorganizare judiciară, cu impact estimat de 1,2 mil. € | Echipa, coordonată de Mihai Popa (Deputy Managing Partner)
Filip & Company a gestionat juridic IPO-ul Christian Tour, încheiat cu succes. Au fost atrase fonduri de 149 mil. lei pentru accelerarea consolidării prin M&A, extindere organică și transformare digitală
NNDKP a asistat Raiffeisen Bank România în legătură cu finanțarea grupului Monza Ares în vederea achiziției Brain Institute și integrării acestuia în structura grupului | Alina Radu (Partener) și Cătălina Dan (Asociat Senior), în prim plan
Mitel & Asociații a asistat vanzatorii în tranzacția prin care Grupul Monza Ares, susținut de Highlander Partners, a preluat centrul privat de neurochirurgie Brain Institute | Mădălina Mitel, coordonatoarea echipei de proiect: ”Pentru noi, un mandat de M&A reușit este acela în care soluția juridică susține logica economică a tranzacției și permite părților să meargă mai departe cu un proiect viabil”
NNDKP a asistat grupul PPC în procesul de negociere pentru încheierea noilor contracte colective de muncă | Roxana Abrașu (Partener) și Daniel Stăncescu (Managing Associate), în prim plan
RTPR asistă Silcotub la achiziția Artrom Steel Tubes. Echipa, coordonată de Mihai Ristici (Partener) și Vlad Stamatescu (Counsel)
Florian Nițu (PNSA), singurul avocat din România aflat în cursa pentru titlul „CEE Partner of the Year” la ”Legal 500 Central and Eastern Europe Awards 2026” - nu doar într-un an mai bun, ci după două decenii de consecvență în excelență: „Avocatul a devenit, în fapt, un ‘integrator’ în proiectele complexe, responsabil de alinierea componentelor juridice, comerciale și operaționale ale unei tranzacții. Clientul este azi un partener strategic, sofisticat și continuu implicat în gestionarea serviciului avocațial”
Mandatele sofisticate, în care soluțiile juridice trebuie dublate de înțelegerea mecanismelor economice, confirmă forța practicii de Insolvență & Restructurare a ZRVP, evidențiată în Tier 1 de Legal 500 | Alexandru Iorgulescu (Partener): ”Pot spune că specific practicii noastre sunt mandatele complexe ce reclamă soluții inovatoare, unde lucrăm adesea pe drumuri ‘neumblate’ și în care problemele de dreptul insolvenței se întrepătrund cu cele civile, societare, administrativ-fiscale”
NNDKP a asistat Grupul Saica în legătură cu achiziția Grupului Thimm. Echipa, cordonată de Gabriela Cacerea (Partener)
18 firme de avocatură și 22 de avocați din România, pe lista scurtă pentru Legal 500 - Central and Eastern Europe Awards 2026. Avocați de la Filip & Company, CMS, RTPR, NNDKP, TZA, Bondoc & Asociații și Schoenherr intră în competiție pentru premii regionale, iar Florian Nițu (PNSA) este nominalizat la titlul de ”CEE Partner of the Year”. Doi legal manageri concurează la titlul de ”In-house Lawyer of the Year” în CEE
Ritm alert, tranzacții de referință și expertiză recunoscută | Practica de Energie & Resurse Naturale a RTPR, Tier 1 în Legal 500, gestionează integrat mandate care combină M&A, finanțări verzi, autorizare și reglementare, oferind clienților internaționali și locali suport în proiecte cu miză ridicată. De vorbă cu partenerul Bogdan Cordoș despre tendințele anului 2026, interesul investitorilor și mandatele relevante
ZRVP organizează în data de 11 iunie 2026 dezbaterea „Contractul de antrepriză: de la FIDIC la HG 1 ̸ 2018 – evoluție, adaptare sau compromis?”
Citeste pe SeeNews Digital Network
-
BizBanker
-
BizLeader
- in curand...
-
SeeNews
in curand...









RSS





